Ethiopia is moving ahead with plans for one of the biggest aviation projects ever undertaken on the African continent: a $12.5 billion international airport designed to handle up to 110 million passengers every year.
Known as Bishoftu International Airport, the proposed facility will be located near the town of Bishoftu, approximately 40 kilometres southeast of Addis Ababa. It is being developed by Ethiopian Airlines as part of a long-term plan to expand the country’s aviation capacity and strengthen its position as a major international travel hub.
Construction officially began on January 10, 2026, when Ethiopian Airlines and government officials held the project’s groundbreaking ceremony. The airport is expected to have four runways and parking space for up to 270 aircraft.
A major expansion of African aviation
The scale of the proposed airport is significant. Its first phase is designed to accommodate 60 million passengers annually, while the completed masterplan provides for a capacity of 110 million passengers.
For comparison, Addis Ababa’s existing Bole International Airport has an expanded annual capacity of approximately 25 million passengers. The new airport is intended to operate alongside Bole, providing additional room for Ethiopian Airlines’ growing passenger and cargo operations.
The project is expected to be completed in phases, with the first phase targeted for 2030. Once operational, it is intended to improve connections between African cities and international destinations, support tourism and create additional opportunities for air cargo and trade.
How will Ethiopia finance the project?
Ethiopian Airlines plans to contribute around 30 per cent of the project cost, with the remaining amount expected to come from international lenders and financial institutions.
The African Development Bank has been appointed as the lead financial arranger and has pledged $500 million towards the project, subject to its financing process. Other institutions and commercial lenders from Europe, the Middle East, China and the United States have also expressed interest.
However, financing remains an important part of the project’s progress. In August 2026, Ethiopian Airlines CEO Mesfin Tasew disclosed that expressions of interest from potential financiers amounted to about $8.5 billion, but financing agreements had not yet been signed as lenders continued their due diligence.

What is happening with construction?
Although the groundbreaking ceremony took place in January, the project has encountered adjustments to its construction timetable.
Ethiopian Airlines initially expected to select its main construction contractors in August 2026. However, the process was postponed to early January 2027 after prospective bidders requested additional time to prepare their proposals, arrange financing and engage subcontractors.
The airline has maintained that the revised bidding schedule will not affect the project’s overall implementation plan.
What this could mean for Africa
Bishoftu International Airport is being planned as more than a new airport for Ethiopia. Its long-term ambition is to strengthen connections across the continent, make international travel more accessible and support the movement of goods between African markets and the rest of the world.
The project also comes at a time when improved transport links are important to the success of the African Continental Free Trade Area (AfCFTA), which seeks to expand trade among African countries.
If completed as planned, Bishoftu could give Ethiopia a much larger role in international aviation while creating another major gateway for African travel, tourism and commerce.